RUBRIK VOLUME 135 :
 
o PROJECT UPDATE
o PROJECT COLLABORATION
o TENDER UPDATE SELASA
o TENDER UPDATE RABU
o TENDER UPDATE KAMIS
o TENDER UPDATE JUMAT
 
PROJECT UPDATE
New & Carry Forward Outlook Eksploitasi Migas — Oktober 2026
PERTAMINA HULU ROKAN
CLUSTER AKTIVITAS TERPADAT
Data Oktober menunjukkan aktivitas PHR tersebar di banyak field.


BANGKO
P_BNKO26_0001
New
Durasi ±23,79 hari
Target Kedalaman ±2.100*

P_BNKO26_LQR_PX02F
New
Durasi ±20 hari
Target Kedalaman ±1.900*


BEKASAP
P_BEKA26_0005
New
Durasi ±18,48 hari
Target Kedalaman ±3.400*

P_BEKA26_0005HW
New
Durasi ±38,3 hari
Target Kedalaman ±5.050*


DURI
2H-0307A
2H-0907A
2H-1007A

Durasi masing-masing ±7,87 hari
Target Kedalaman ±850*

P_9M0903A
P_9M0902A
P_9M1001A

Durasi masing-masing ±7,9 hari
Target Kedalaman ±820*

T_9M0802T

Durasi ±6,87 hari
Target Kedalaman ±850*


KOTABATAK
P_KOTA26_0001HW_MSF
New
Durasi ±96,5 hari
Target Kedalaman ±7.500*

KOTA00471D1_DP
New
Durasi ±23,7 hari
Target Kedalaman ±5.500*

KOTA00524D1_DP
New
Durasi ±23,7 hari
Target Kedalaman ±5.500*


MINAS
P_MINA26_0004HW
New
Durasi ±30,51 hari
Target Kedalaman ±5.600*

P_MINA26_0005HW
New
Durasi ±32,77 hari
Target Kedalaman ±5.600*

P_MINA26_0007
New
Durasi ±30,51 hari

P_MINA26_0008
New
Durasi ±30,51 hari


RANTAUBAIS
-J4-49A
-J4-74A
-J4-77A
-J4-85A
-J4-86A

Durasi masing-masing ±8,9 hari
Target Kedalaman ±850*

P_RABA_RDD1
Durasi ±12,97 hari
Target Kedalaman ±850*

*) Angka target kedalaman mengikuti database sumber.


DATA SIGNAL:
Aktivitas PHR tidak homogen.

Ada aktivitas sekitar:
7–9 HARI

tetapi terdapat pula:
P_KOTA26_0001HW_MSF
±96,5 HARI

Perbedaan ini layak digali.
Jangan memperlakukan seluruh aktivitas PHR sebagai satu kebutuhan teknologi yang sama.

FIELD
→ WELL
→ DURATION
→ DEPTH
→ TECHNICAL PROGRAM

Dari sinilah kebutuhan proyek sebenarnya mulai dapat dipetakan.

Gallery Album

 
All Rights Reserved © Copyright 2024 PT. Tender Indonesia Commercial, design by AbelPutra.com