PROJECT UPDATE
Data Intelligence — Workover Oktober 2026 PHE Sanga Sanga: EOR & PNW
Cluster berikutnya memperlihatkan pekerjaan dengan durasi dan indikasi biaya yang lebih besar.

CLUSTER EOR
- EOR-11 — Change Layer — 8,17 hari — US$71.500
- EOR-12 — Change Layer — 8,17 hari — US$71.500
- EOR-21 — Well Conversion — 8,17 hari — US$71.500


CLUSTER PNW
- PNW-5 — Change Layer — 12,5 hari — US$83.900
- PNW-6 — Change Layer — 12,5 hari — US$83.900
- PNW-7 — Change Layer — 12,5 hari — US$83.900
- PNW-8 — Change Layer — 12,5 hari — US$83.900
- PNW-16 — Change of Lift System — 12,5 hari — US$83.900
- PNW-22 — Change of Lift System — 12,5 hari — US$83.900
- PNW-23 — Change of Lift System — 12,5 hari — US$83.900
- PNW-24 — Change of Lift System — 12,5 hari — US$83.900
- PNW-26 — Fracturing — 12,5 hari — US$83.900

Data PNW menarik karena dalam satu cluster terdapat Change Layer, Change of Lift System hingga Fracturing. Artinya, kebutuhan teknologi dan jasa dalam satu program PHE Sanga Sanga pun tidak selalu sama.

SUMUR → JENIS INTERVENSI → DURASI → BIAYA → KEBUTUHAN TEKNOLOGI

Inilah informasi yang selanjutnya dapat diterjemahkan menjadi peluang vendor.