WK Duyung | Offshore Natuna | Kepulauan Riau, Indonesia
Knowledge Type: Project Intelligence + Supply Chain Intelligence Opportunity Status: ACTIVE DEVELOPMENT Opportunity Approach: Penetrate the Supply Chain After Main Contract Award
---
# 1. PROJECT IDENTITY
Project Name: Mako Gas Field Development Field: Mako Gas Field / Lapangan Gas Mako Working Area: Duyung Working Area / WK Duyung Operator: West Natuna Exploration Limited (WNEL) Parent / Affiliation: Conrad Asia Energy Sector: Oil & Gas Subsector: Upstream Gas / Offshore Field Development Commodity: Natural Gas Location: Laut Natuna, Kepulauan Riau, Indonesia Project Type: Offshore Gas Field Development Project Stage: Development / Execution FID: March 2026 Target First Gas: Q4 2027 CAPEX to First Gas: Approximately US$320 million
---
# 2. RESERVES & PRODUCTION
Gross 2P Reserves: Approximately 330 Bcf Target Plateau Sales Gas: Approximately 111.9 MMscfd Gas Market: Domestic Indonesia Gas Offtaker: PT PLN Energi Primer Indonesia / PLN EPI
Mako merupakan lapangan gas offshore yang dikembangkan untuk meningkatkan pasokan gas bagi pasar domestik Indonesia.
---
# 3. DEVELOPMENT CONCEPT
Tahap awal pengembangan Mako mencakup:
6 Development Wells
↓
Tie-Back System
↓
Leased Mobile Offshore Production Unit — MOPU
↓
Gas Pipeline ±59 km / 18 inch
↓
KF Platform — Kakap PSC
↓
West Natuna Transportation System — WNTS
↓
Domestic Gas Market / PLN EPI
---
# 4. PROJECT FACILITIES
Fasilitas utama yang terkait dengan pengembangan Mako meliputi:
6 offshore development wells Conductor Support Frame / CSF Leased MOPU Subsea production system Flowlines Risers Umbilicals ±59 km gas pipeline 18-inch gas pipeline Tie-in to KF Platform Connection to WNTS Offshore installation facilities
---
# 5. PROJECT TIMELINE
FID March 2026
↓
Engineering & Procurement
↓
Fabrication
↓
Rig Mobilization Target Q2 2027
↓
Drilling — 6 Development Wells
↓
CSF / SURF / Offshore Installation
↓
Hook-Up & Commissioning
↓
FIRST GAS Target Q4 2027
---
# 6. MAIN CONTRACT / CONTRACTOR MAP
## PACKAGE 01 — CONDUCTOR SUPPORT FRAME / CSF
Main Contractor: PT PAL Indonesia
Contract Type: EPCT
Scope mencakup:
Engineering Procurement Fabrication Assembly Transportation to offshore location
Pipeline Length: Approximately 59 km Pipeline Diameter: 18 inch Destination: KF Platform — Kakap PSC Further Connection: West Natuna Transportation System / WNTS
Development concept menggunakan leased Mobile Offshore Production Unit / MOPU.
### Potential Opportunities
Process equipment Mechanical equipment Rotating equipment Pumps Compressors Valves Piping Instrumentation Control system Electrical equipment Power generation Fire & gas system Safety equipment Maintenance Inspection Production support services
Mako | Mako Gas | Mako Gas Field | Lapangan Mako | Lapangan Gas Mako | WK Duyung | Duyung PSC | West Natuna | Natuna | Laut Natuna
### Company Keywords
WNEL | West Natuna Exploration Limited | Conrad Asia Energy | PT PAL Indonesia | PAL Indonesia | PT Timas Suplindo | Timas | PDSI | ADES | PLN EPI | PLN Energi Primer Indonesia
### Drilling Keywords
Drilling | Pengeboran | Pemboran | Development Well | Sumur Pengembangan | Jack-Up | Jackup | Drilling Rig | Admarine 502 | Casing | Tubing | Cementing | Completion
Pipeline | Pipa Gas | Gas Pipeline | 18 Inch Pipeline | WNTS | West Natuna Transportation System | KF Platform | Kakap PSC
---
# 15. OPPORTUNITY CLASSIFICATION
Opportunity Type: Active Project / Supply Chain Opportunity Project Maturity: High Project Stage: Development / Execution Tender Status: Several Main Contracts Awarded Supplier Opportunity: ACTIVE Business Development Priority: HIGH
### Important RAG Interpretation
MAIN CONTRACT AWARDED ≠ BUSINESS OPPORTUNITY CLOSED
Main contract award justru dapat membuka peluang baru bagi:
“Proyek Mako memiliki CAPEX sekitar US$320 juta dan First Gas ditargetkan Q4 2027.”
AI harus mampu melanjutkan:
“Proyek Mako telah memasuki tahap development. Beberapa kontrak utama telah diberikan kepada PT PAL Indonesia untuk CSF, PT Timas Suplindo untuk SURF EPCI, serta PDSI–ADES untuk drilling enam development wells. Karena itu peluang saat ini bergeser ke supply chain di bawah main contractor, termasuk drilling equipment, casing & tubing, coating, pipeline materials, subsea equipment, marine logistics, HSE, inspection dan technical manpower.”